AI 基礎設施
NVIDIA DSX MaxLPS Dynamically Allocates Rack Power, Boosting GB200 Inference Performance per Watt by 1.5×
DSX MaxLPS uses real-time telemetry to reallocate unused power. NVIDIA found that the provisioned power for a GB200 NVL72 rack could be reduced from 125 kW to 90 kW while maintaining throughput. The solution also combines workload-specific power profiles with 45°C liquid cooling, but its core Dynamic Power Software remains in Developer Preview.

NVIDIA has disclosed further details about how DSX MaxLPS works. Instead of permanently reserving power for each GPU rack based on its theoretical peak, Dynamic Power Software (DPS) builds a topology spanning power infrastructure, resource groups, racks, nodes, and GPUs. It continuously monitors actual power consumption and reallocates unused power capacity within administrator-defined budgets and policies. The control loop updates GPU power limits, verifies that groups remain within their aggregate budgets, and handles maintenance or emergency load-shedding events on a best-effort basis.
In a representative inference test published by NVIDIA, MaxLPS reduced provisioned rack power from 125 kW to 90 kW while a GB200 NVL72 ran Kimi-K2.5 at FP4 precision. With total facility power held constant, this could theoretically accommodate 39% more racks and improve performance per watt by about 1.5×. In another test using DeepSeek-R1 at FP4 precision, provisioned power fell from 136 kW to 101 kW, potentially allowing about 35% more racks and improving performance per watt by 1.3× to 1.4×. This is not achieved through downclocking alone: APPM applies prevalidated power profiles based on whether workloads involve inference, training, memory-bound processing, or compute-bound processing, while Dynamo can further optimize inference topologies across racks.
MaxLPS also requires support from facility infrastructure. Design targets for Vera Rubin NVL72 include a coolant inlet temperature of 45°C, enabling data centers in suitable climates to reduce their reliance on compressor-based chillers and redirect cooling power to compute. DSX Exchange can connect DPS with building management, power, cooling, and scheduling systems through a NATS event bus, but it is not required for MaxLPS.
Engineering teams should not directly incorporate the claim of “40% more GPUs” into capacity budgets. These figures are based on NVIDIA-selected models, numerical precision, throughput targets, and its own platforms, and they have not yet been independently reproduced across models. Public materials also contain inconsistent Vera Rubin/GB300 labeling for the second test platform. DPS remains available only to approved early-preview customers, and real-world gains will depend on latency, error rates, peak power consumption, redundancy policies, and site cooling conditions. A more reliable adoption approach is to compare static provisioning with DPS-managed results at the same service level before deciding whether to increase rack density.